November 2004, shop refurbishment
| December 2004, new stairs to shop rear
| May 2005, tidied storeroom and lobby
| June 2006, tidying up rear yard and garden
| January 2007, checking roof for winter damage
|
December 2007, first floor flat before refurbishment
| August 2008, replacement roof, second floor flat, almost three months on and the builder still hasn't finished
| September 2008, replacement roof three months on, second floor flat, leaking at joins and window
| November 2008, changed builder, second floor flat, all work finished
| January 2009, first floor flat, fully refurbished
|